The Texas Department of Transportation is busy pouring concrete on the Beltway 8 frontage road, making progress amidst some unexpected challenges.

Update details from Texas Department of Transportation on Beltway 8 frontage road construction.
Update on the Beltway 8 frontage road project in the Pasadena area. Crews are currently pouring new concrete pavement between Pasadena Blvd. to Red Bluff Rd on the northbound side. Crews will then continue to work placing new pavement on the northbound side between Fairmont and Spencer in the coming weeks.

TxDOT continues to address utility issues with the project, which has required some modifications to the drainage. This has altered the scheduled at times but the TxDOT Southeast Area Office remains committed in working with the contractor to move the project along and get as much work done as possible.

We sincerely thank the community for their patience as we work through completing this project. For closures related to the project go to www.houstontranstar.org and to submit a concern about the project go to https://www.txdot.gov/about/contact-us/report-an-issue.html.

City of Pasadena